Broad Street parkway BroadStreetParkway

The idea of a road connecting Broad Street with Hollis Street, providing a third crossing of the Nashua River and a way for traffic to avoid Library Hill, has been discussed since at least the 1960s. In 2008, Board of Aldermen vote approving a $37.6 million bond to build the Broad Street Parkway, and in 2011 the city began demolition work in the Millyard. A final design is being drawn up and no completion date is settled, but the road is on its way. This page collects past and ongoing Telegraph coverage of the issue.

Click here to download a very detailed map of the current proposed route of the parkway, taken from the Web site of the city. The map show details down to individual buildings, but as a result it is too large to be seen online and must be downloaded and viewed with a PDF reader. It is roughly 1 Mb in size andd can take a long time to download, depending on your Internet connection.



pdf

Articles

Broad Street Parkway project coming into focus

BSP050412

NASHUA – The Broad Street Parkway is like a Polaroid photo, each traffic sign, guardrail and foot of concrete slurry sharpening into focus moment by …

Aldermen vote unanimously to encourage city to preserve millyard chimney

MillyardChimney0425

NASHUA – A structural analysis of the Millyard chimney has concluded that even with restorative work, the historic structure would need to be cut down …

Interactive map walks users through the Broad Street Parkway

ParkwayMap0424

NASHUA – The Broad Street Parkway is one of the most complicated projects ever undertaken by the city, so it makes sense that it’s now …

Asbestos delays demolition of Nashua’s Boiler House building

BoilerHouse0423

NASHUA – Additional asbestos located in the building known as the Boiler House will delay the building’s demolition at an extra cost to the city. …

Bronstein residents say they are still in the dark about demolition, relocation plans

BronsteinUpdate0417

NASHUA – For Jorge De Leon’s family, the future is uncertain. The Bronstein Apartments, where De Leon lives with his wife and three daughters and …

Aldermen want Nashua’s millyard chimney restored to historic height

ChimneyRecommend0405

Whether Nashua’s prominent Millyard chimney was historically 150 or 180 feet tall, aldermen want it restored to its original height again. Last week, the aldermen’s …

Broad Street Parkway construction begins in Tree Street area of city, Palm and Pine streets affected

BSP0405

NASHUA – An early taste of the Broad Street Parkway has begun with a $2 million street project in the city’s Tree Streets area. The …

That thunder you hear might be heavy trucks rumbling through the Tree Streets

NASHUA – Sometimes there are unforeseen delays, disruptive noises and unanticipated traffic detoured through your neighborhood. And that just describes the meeting Thursday concerning reconstruction …

Palm Square to host meeting related to parkway street project

ConstructionMeetingAdv032612

NASHUA – Continuing a trend, a meeting to update residents on road and sewer work related to the Broad Street Parkway will be held in …

Broad Street Parkway project moves forward with boiler house demolition

Boilerhouse0319

NASHUA – As demolition crews remove the roof to the building commonly referred to as the Boiler House, residents are getting their first glimpse of …

Top Millyard makeover plan picked

NashuaDesignContest0320

NASHUA – A Millyard makeover design, honoring the so-called Boiler House currently under demolition to make space for the Broad Street Parkway, was selected Tuesday …

Pastor concerned about lack of information about Parkway plans

Displaced022712

NASHUA – It’s hard to grow or even retain a congregation knowing your church has to move, but without knowing when or where. That’s the …

Nashua aldermen to consider fate of Millyard chimney

Chimney021412

NASHUA – You can see the Millyard chimney from miles away. Now, at least one alderman wants to put it on record that no matter …

Leon Kenison, Broad Street Parkway project manager, dies at 70

newsKennisonDies0213

One summer day some years ago, Bill Boynton, public information officer for the N.H. Department of Transportation, needed to touch base with his boss on …

Parkway designs beauty to behold

Since construction is in the early stages, it’s much too soon to know what the Millyard and Tree Streets neighborhood will look like when the …

Nashua board to review Broad Street Parkway contract

NASHUA – With Broad Street Parkway construction slowly getting underway, the city wants to hire an experienced hand to keep the project moving smoothly. The …

Plenty of ideas for Nashua Millyard makeover narrowed down to 8 submissions

BSPDesigns020112

NASHUA – Given license to dream, several people dreamed big on reshaping the downtown Millyard. These paper dreams included an underground roadway, on-site wastewater treatment, …

Nashua Broad Street Parkway design contest moves forward

NASHUA – With the Broad Street Parkway expected to open up access to the Millyard area, the city has solicited designs for a new and …

Dispute about transparency of Nashua’s Broad Street Parkway project lingers

NASHUA – The Broad Street Parkway has a long and complicated history, so it’s no surprise that the impending construction of the two-lane roadway continues …

Nashua board approves parkway design contract after much debate, talk about taking less of depot section

Parkway122811

NASHUA – As the Broad Street Parkway project moves forward, Mayor Donnalee Lozeau seems to be striking a balance between addressing concerns about protecting the …

Nashua aldermen approve Broad Street Parkway design contract

BOAparkway1227

NASHUA – After lengthy discussion about government transparency, the historic value of buildings and the need for modern transportation, aldermen Tuesday approved a $1.5 million …

Historic buildings vs. Broad Street Parkway in city hearing

BSP1222

NASHUA – A sharply divided city finance committee voted 3-2 Tuesday to send a proposed $1.5 million contract for the design of the Broad Street …

Submit your own design for Nashua parkway neighborhood

NASHUA – If it worked for Greece’s Acropolis and New York’s Central Park, maybe it can also work in this old mill city. Those famed …

Nashua church has faith about moving from path of parkway

ParkwayBuildings120911

NASHUA – The parishioners of Faith Baptist Church won’t worry too much about losing their place of worship to the looming construction plans for the …

Broad Street Parkway moving toward a big start

Parkway120111

NASHUA – The Broad Street Parkway project continues to take small but important steps toward its long-awaited construction. Work has started on the removal of …

Landmark chimney may need renovations to meet state requirements for Nashua parkway construction

BSP1021

NASHUA – With roadwork for the Broad Street Parkway expected to begin sometime next year, the city has started preparations for the two-lane road. The …

Chimney work starts Parkway project

MillyardChimney051311

NASHUA – Work on the long-awaited Broad Street Parkway construction project has officially begun. No, the city isn’t laying blacktop or even clearing the way …

Beyond debate: Nashua Broad St. Parkway session was forum to inform

NASHUA – This wasn’t the time for another debate on whether the Broad Street Parkway should be built. That issue has long since been decided, …

Judge rules against city developers

NASHUA – A judge has ruled against the Tamposi brothers in a dispute over whether delays in the Broad Street Parkway amounted to a taking …

Lost deals blamed on project delays

ParkwayLawsuit1019

NASHUA – Confusion over how much land would need to be taken for the Broad Street Parkway and delays in the construction sunk proposed real-estate …

Green light for Broad St. Parkway

NASHUA – The Broad Street Parkway has cleared another hurdle, with the federal highway administration issuing a revised “Record of Decision” that allows the project …

New park is best use of former Labine site

Nashua will some day have an attractive new gateway to the downtown to complement the completion of the Broad Street Parkway, thanks to a visionary …

Broad St. impact is issue

BSPmeeting0702

NASHUA – A half-hour into the drop-in informational session Monday, nearly 50 people already had shown up to browse the maps and charts and chat …

Nashua...From the inside

Do you remember the Broad Street Parkway? With other city projects in the works – acquiring a water utility and trying to save a historic …

Park a good option for Labine property

When we last wrote about the fire-ravaged Labine building back in February, we held out a smidgen of hope that the historic “flat-iron” building with …

Broad Street Parkway plan to get $487k in funding

NASHUA – The $60.4 million Broad Street Parkway project has been OK’d for an additional $487,000 in federal money to add sidewalks to the cross-city …

Informational session on Broad Street Parkway held in Nashua

NASHUA – A drop-in informational session about the Broad Street Parkway on Thursday evening drew some familiar opponents to the roadway but also drew curious …

City to hold info session on parkway

NASHUA – It’s been a dozen years since federal highway officials signed off on the then proposed and now approved Broad Street Parkway. Before construction …

Nashua...From the Inside

City could net BSP funds

BSP – maybe the acronym at least could stand for "Big Sidewalk Path." The city may get $500,000 in federal dollars to add sidewalks to …




ClassifiedsNH.com